Consumption/ Receipt of RM against Assigned Issues- Internal

Previous pageReturn to chapter overviewNext page
Show/Hide Hidden Text

bullet01 Consumption and Receipt of RM against assigned issues may help you to find out the actual cost of production by determining the consumption of raw material. See below how to use this feature in LOGIC ERP Software.

 

Consumption/ Receipt of RM against Assigned Issues- Internal: Main Menu> Production> Raw Material Processing> Consumption/ Receipt of RM against Assigned Issues - Internal

 

Toggle Icon Minus 17Main Menu

 

main menu consumption

 

Fig 1. Main Menu

 

 

bullet01 Consumption/ Receipt of RM against Assigned Issues- Internal window will appear on your screen. Enter details including configuration for Receipt Register, Received From, Customer Ref. No, Bill No, Document No, Receipt Date and Receipt Time. Click on 'Select Issue'.

 

bullet01 Issue Register Search window will appear on your screen. Select the Job Order Issue and click on Ok.

 

STITCHING CONSUMPTION

 

Fig 2. Select Issue

 

bullet01  Add Issue window will appear on your screen. Select Issue and click on Ok.

 

STITCHING CONSUMPTION 1

 

Fig 3. Add Issue

 

bullet01  A window will appear on your screen. Here, you can get a receipt of consumption, returned or waster raw material . Click on 'Save' button to save it.

 

STITCHING CONSUMPTION 2

 

Fig 4. Consumption/ Receipt of RM against Assigned Issues

 

Back To Top